Citaat:
Oorspronkelijk geplaatst door Micele Bekijk bericht
voor 50 kW heb je al minstens 10 aaneengeschakelde powerwalls nodig en dan zit je op 145 kWh capaciteit volgeladen. (230 Volt)
Zal véél goedkoper uitvallen.

https://www.tesla.com/sites/default/...tasheet_nl.pdf
Tikfoutje moet 135 kWh zijn.

héhé, toevallig heeft in UK "iemand" dat voorgedaan, het gemeentehuis van Portsmouth, 250 kWp extra zonnepanelen hebben ze nu, en 135 kWh opslag (10 powerwalls) genomen. Als je maar kunt wachten krijg je ze wel.

Citaat:
https://www.energymanagermagazine.co...mouth-greener/

New Solar and Tesla Batteries help to make Portsmouth Greener

10 December 2020



A new large 250 kilo-watt (kW) solar system has been installed on the roofs of Portsmouth City Council’s Hilsea Industrial Estate. This complements the existing 50kW system and completes the biggest single solar and battery installation for the council to date. It marks another important step towards the council’s target of net zero carbon by 2030, with solar and batteries being identified as one of the key technologies to deliver the renewable power needed.

This ground-breaking project uses batteries as a key component of the installation; installed alongside 738 solar photovoltaic (PV) panels. The ten-unit battery system, is the largest operational Powerwall installation in the UK. The system can store 135 kWh of electricity at any one time; enough to power an average domestic homes for 2 weeks. As well as capturing more of the solar power generated on the site, the batteries are also able to take advantage of storing power at night, when electricity is cheaper. Stored energy is then used during mornings and early evenings when electricity costs are more expensive.

Combined, the solar PV and storage will reduce the site’s reliance on grid-bought electricity by almost 50%; despite there being many energy-hungry processes at the industrial estate. The system will reduce carbon emissions by 69 tonnes a year, and reduce the running costs of the site significantly. During the summer months, virtually all of the power required to run the site will be coming from either the panels or batteries.

Cllr Dave Ashmore, the council’s Cabinet Member of Environment and Climate Change said: “It’s fantastic to see Portsmouth City Council leading the way when it comes to innovative projects like the one at Hilsea Industrial Estate. Not only are we producing and using our own renewable energy but projects like this dramatically reduce the Council’s ongoing energy costs. The Council has been clear in setting out its plans in tackling climate emergency and it’s fantastic to see projects like acting out these plans.”

The work was carried out by one of Portsmouth City Council’s Solar PV framework contractors, Evo Energy and project managed by the City Council’s in-house Energy Team.

The council has already used its framework to install Tesla Powerwalls in 13 housing blocks, with a further 20 on the way. However, this is the first time that such a large number of the units have been used in a single installation. Where batteries have been installed previously, up to 98% of the sites’ electricity demand has been met through the batteries and accompanying solar.

Energy storage through the use of batteries is set to become a key technology for Portsmouth City Council and their ambitions to become net zero carbon by 2030; as they strive to take every opportunity to harness renewable energy opportunities.